The Waimea Community Dam reservoir, pictured on 30 August, is being filled in stages. Photos: Supplied.
Speculation about issues with the Waimea Community Dam are “unfounded”, according to Waimea Water Ltd’s chief who says the dam is performing as expected.
Rumours have been circulating that the dam was not holding water above a certain level, however, Waimea Water Ltd chief executive Mike Scott says that through July and August the reservoir was managed to a very low water level to allow the isolating valve to be installed.
He says the dam is performing as expected and any teething issues are being addressed.
“It is early days, and we will assess and verify dam performance as we fill the reservoir in stages,” Mike says.
Testing at the Waimea Community Dam has been progressing through the winter, and Waimea Water Ltd expects to commence filling the reservoir imminently, now that the sealing concrete plug and isolating valve have been installed.
“Speculation about there being issues with the dam are unfounded. We are comfortable with how the dam is performing. It is doing what we expected and contemplated, and we are executing our commissioning plans.”
The reservoir will be filled in stages by keeping the water level at hold points for extended periods to allow for testing and engineering measurements.
Mike says, when it rains there will be times when water will need to be released to return the reservoir to a set level, and then when ready, the reservoir level will be built up to the next hold point.
“What we most need now is average rainfalls in the dam’s catchment area. It has been very dry recently, but based on advice we are optimistic about the spring weather. With sufficient rainfall we expect to provide water to shareholders and the community this summer,” he says.
The dam, a public private partnership between the Tasman District Council and Waimea Irrigators, is the first large dam to be constructed in New Zealand in 25 years. The reservoir will eventually hold 13 million cubic metres of water to provide water security to the region.
“By having the reservoir full and dam commissioned by December, we can provide our shareholders and community with confidence ahead of the forecasted windy and dry El Nino summer.”